Business Case
- Customer wanted an automation solution for 400kV, 220kV substations in the plant
Systems and Tools
- SIMATIC Digsi 4.9 & 5.0
- SICAM PAS 8.06
- SIMATIC WinCC 7.4
- Siemens Combustions Controls
- HMI system & PAS Server system is communicated by Industrial Ethernet
Project Scope
- Design and develop Graphics for the system
- IO/ Loop test
- Handover activities and Snags clearances
- Extended Pre-commissioning and Commissioning support for the project